Beyond traditional evm: earned schedule as a time-based alternative for schedule performance measurement in epc projects a case study at sarpi
Loading...
Date
Journal Title
Journal ISSN
Volume Title
Publisher
Finance and Business Economics Review
Abstract
EPC project monitoring at SARPI relies on classic EVM indicators,
which have known structural weaknesses for schedule tracking. This study used
semi-structured expert interviews plus quantitative analysis of EVM versus
Earned Schedule (ES) across three completed EPC projects. Findings show
universal EVM use but no awareness of ES among institutions surveyed.
Empirically, ES outperformed EVM in three ways: better detection of schedule
deviations late in projects when SPI becomes unreliable, accurate time-based
representation of schedule variance without distortion, and more precise duration
forecasts (IEAC) early enough to enable preventive action.